New single-lane bridge to cross Sungai Layun at Long Kevok

Soil investigation works for the construction of a new single-lane bridge crossing Sungai Layun at Long Kevok, in the Miri division, has just been completed.

Piling works have begun for the foundation of the reinforced concrete bridge, which will be followed by groundworks for roads and drainages.

The infrastructure project is implemented by the Highland Development Agency (HDA), under RECODA. It is expected to be completed by the middle of this year.

New bridge crossing Sungai Layun at Long Kevok

A new single lane bridge crossing Sungai Layun at Long Kevok, in the Miri division will be constructed in an infrastructure project implemented by the the Highland Development Agency (HDA), under RECODA.

Excavation for roadside drains and piling works for the concrete bridge are ongoing, while a temporary bridge diverts traffic. The project is expected to be completed by this year.