Nanga Machan bridge, Kanowit 44% complete

Construction of the Nanga Machan bridge, in the Kanowit District is over 44% complete, while the road and paving works for a connecting road is 80% complete.

The 130-metre reinforced concrete bridge will cross Sungai Kanowit, with construction expected to be completed by this year.

The infrastructure project also involves the upgrade of Jalan Ulu Machan, whereby 9.5km of the existing earth road will be upgraded to R1 Standard.

The infrastructure project is implemented by the Upper Rajang Development Agency (URDA), under RECODA.

Construction of Ngungun / Jagau road, Kanowit

A 10.8km Ngungun / Jagau road is being constructed in the Kanowit District in an infrastructure project implemented by the Upper Rajang Development Agency (URDA), under RECODA.

The R1 standard tar sealed road will link Nanga Nirok and Nanga Bat. The project also involves the construction of two Bailey bridges.

Soil investigation works is nearly completed while construction works especially site clearance have begun. The project is expected to be completed by next year.

New road to link Ngungun and Jagau, in Kanowit

A 10.8km tar sealed road will be built to connect Ngungun and Jagau, in Kanowit, in an infrastructure project implemented by the Upper Rajang Development Agency (URDA), under RECODA.

The project will include the construction of spur roads as well as two bridges. Site clearing, earthworks, the construction of culverts and geotechnical works are underway.

The project is expected to be completed next year.

Concreting of Nanga Machan bridge in progress

Construction of a 130-metre Nanga Machan bridge, in the Kanowit District is ongoing, with fabrication of reinforcement cages for I-Girders and concreting in progress.

With bored piling works done, construction of the embankment slab has begun. Roadworks for Jalan Ulu Machan is also in progress, whereby 9.5km of the existing earth road will be upgraded to R1 Standard.

The reinforced concrete bridge will cross Sungai Kanowit, with construction expected to be completed by this year.

The infrastructure project is implemented by the Upper Rajang Development Agency (URDA), under RECODA.