BOULEVARD ROAD PACKAGE 1 by Hock Seng Lee
Date: 30th April 2017
Project name:
SCORE – Taman Perindustrian Samalaju: Penyediaan Tapak dan Infrastruktur (I) – Phase 5 Stage 1;
Proposed Samalaju Boulevard Package 1
Division: Bintulu Development Authority (BDA)
Status:
- Cutting works in progress (85%)
- Rock Blasting works (85%)
- Embankment Filling works (90%)
- Drainage works (23%)
- Culvert works (90%)
- Road Sub-base works (40%)
- Road base works (30%)