SECTION B2 ROAD PACKAGE 2

Project: 
Taman Perindustrian Samalaju (Section B2 Road Package 2)

Status:

  1. Filling work.
  2. Embankment cutting
  3. Preparation for static load test

Boulevard Road Package 1

BOULEVARD ROAD PACKAGE 1 by Hock Seng Lee
Date: 30th April 2017

Project name:
SCORE – Taman Perindustrian Samalaju: Penyediaan Tapak dan Infrastruktur (I) – Phase 5 Stage 1;
Proposed Samalaju Boulevard Package 1

Division: Bintulu Development Authority (BDA)

Status: 

  1. Cutting works in progress (85%)
  2. Rock Blasting works (85%)
  3. Embankment Filling works (90%)
  4. Drainage works (23%)
  5. Culvert works (90%)
  6. Road Sub-base works (40%)
  7. Road base works (30%)

SECTION B2 ROAD PACKAGE 1

Project:
Taman Perindustrian Samalaju (Section B2 Road Package 1)

Status:

  1. Embankment cutting and filling.
  2. Culvert concreting work
Access road to Baleh HEP

Access road to Baleh HEP

Enhancing the infrastructure so that people and goods can be transported quickly and easily is vital for development throughout Sarawak. With further improvements to its fine deep water ports, the new Mukah Airport and the major expansion and upgrading of the Trans Borneo highway, the SCORE area is rapidly improving its long distance transport links.

But there is also a lot of less spectacular work going on to improve road connections within the region. The building of the 73km road up to the Baleh Dam hydropower construction site, across hilly and difficult terrain, is just one of many projects that are currently under way. Several phases have already been completed, including the bridge that will take the road across the Baleh River at Nanga Mujung.

Access road to Baram HEP

Project Description : Construction of 64km of R3 sealed road from Jalan Beluru/Lg Lama access road to the proposed Baram Dam site.
Growth Node : Baram

Tanjung Manis Halal Hub Development Access Road

 

The construction of a 5km access road (Parcel 1) to the Tanjung Manis Halal Hub was 75.4% complete in 2015. The project involved putting in place road bases, road pavements and road furniture; water reticulation system; electrical and telecommunication infrastructure; and water retention facility.