Boulevard Road Package 1

BOULEVARD ROAD PACKAGE 1 by Hock Seng Lee
Date: 30th April 2017

Project name:
SCORE – Taman Perindustrian Samalaju: Penyediaan Tapak dan Infrastruktur (I) – Phase 5 Stage 1;
Proposed Samalaju Boulevard Package 1

Division: Bintulu Development Authority (BDA)

Status: 

  1. Cutting works in progress (85%)
  2. Rock Blasting works (85%)
  3. Embankment Filling works (90%)
  4. Drainage works (23%)
  5. Culvert works (90%)
  6. Road Sub-base works (40%)
  7. Road base works (30%)

Mukah Water Supply, upgrading existing water treatment plant

As in all the SCORE development nodes, plentiful, reliable, high quality water supplies for both commercial and domestic use will form an essential part of the infrastructure needed for rapid industrial development in the area.

Impressive progress has already been made on a long-term programme that includes the upgrading of Mukah’s existing water treatment plant, the building of a new booster station and the expansion of the Tingkas Intake Pumping Station. These projects will ensure that supplies of both raw and treated water are available to match the increasing demand as Mukah’s population grows and new investments boost employment and industrial activity.